Planning around Cambodian long holidays

Cargo piles up because the dates were calculated wrong, not because capacity vanished. Count backwards from the day the destination resumes work.

Three dates, not one

01Destination shutdown: clearance, warehousing and delivery can all stop. Long breaks often run loose a day either side.
02Cut-off for receiving: carriers and warehouses stop accepting cargo several days early to clear the floor and arrange cover.
03Resume date: the first two or three days back are a backlog, so clearance and delivery queue again.

The third date is the one people miss. Cargo does not land on the first working day; plan for resume plus two to three days.

Which months matter

In Cambodia the longest and most disruptive breaks are Khmer New Year in mid-April, Pchum Ben in September or October and Bon Om Touk in November. Dates follow the lunar calendar and are announced by the government each year, moving by a few days.

Do not memorise dates. Lock the schedule after the official announcement and update the cut-off calendar once a year.

How to count backwards

01Fix D, the day operations resume.
02Delivery promise = D + 3 days, clearing the backlog.
03Clearance complete = delivery promise − 2 days.
04Arrival at port or warehouse = clearance − 2 days, leaving room for document fixes.
05China departure = arrival − transit days, minus 3 more days for documents.

If the departure date has already passed, wait. Cargo shipped in the final week before a break usually sits in the destination until operations resume, and you pay the storage.

Ship earlier for these

Food, perishables and anything temperature-controlled should not be cutting it fine around a break. Licence-based products slow down before holidays. Trade shows and openings need two to three weeks of buffer.

FAQ

What happens to cargo arriving during the holiday?

Vessels still berth, but clearance and collection can pause, and port storage accrues under port rules. Arriving before a break and clearing after it is the most expensive combination.

How early is the cut-off?

Per carrier and warehouse notice, usually several days before the break. We publish our own cut-off and resume dates ahead of each long holiday.

Can you guarantee pre-holiday delivery?

No. The week before a break is the busiest of the year. What can be committed is shipping before the cut-off on the backwards plan.

We update the cut-off calendar when the official notice lands. If a shipment is racing a holiday, send the product and target date and we will run the backwards plan.